New Acute Hospital For The South West ENNISKILLEN
Progress Update No 17 For Works up to 31st January 2012 Provided By Northern Ireland Health Group
01. Overview / Current Status 
Photograph 1 - (January 2012)

Photograph 2 - (January 2012)

Photograph 3 - (January 2012)

Photograph 4 - (January 2012)

Photograph 5 - (January 2012)

Photograph 6 - (January 2012)

Photograph 7 - (January 2012)

Photograph 8 - (January 2012)

Photograph 10 - (January 2012)
02. Construction Milestones
Construction Milestone | Detail | Target Date | | | | On Site Start-up | Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works | May 2009 | Mock Up Facility | Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms | January 2009 | Topping Out | Building reach roof top level. Superstructure complete. | Quarter 3 2010 | Weather Tight | Building sealed from the elements; Windows, doors & roof. | Quarter 1 2011 | Internal Finishes | Viewing a section of the completed internal works. | Quarter 1 2011 | External Finishes | Landscaping, lighting, signage, way finding. | Quarter 1 2012 | Practical Completion | Construction Phase Complete, ready for Trust Commissioning. | Quarter 2 2012 | Opening | New Hospital opens its doors to patients. | Quarter 3 2012 | Official Opening | Official Opening Ceremony | Autumn 2012 |
03. Subcontractor Appointment
The project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program). A very compliant and qualified local construction industry is prequalifying for involvement in the project.
04. Two Month Look Ahead (01 Feb – 31 March 2012) · All internal fit out and finishes completed · All mechanical and electrical services substantially complete. · Validation and snagging of internal works substantially complete. · Landscaping and external works completed. |