Construction Progresss Update - January 2012

New Acute Hospital

For The

South West

 

ENNISKILLEN

 

 Progress Update

No 17

 

For Works up to 31st January 2012

 

Provided By

Northern Ireland Health Group



01.  Overview / Current Status



Photograph 1 - (January 2012)



Photograph 2 - (January 2012)



Photograph 3 - (January 2012)



Photograph 4 - (January 2012)



Photograph 5 - (January 2012)



Photograph 6 - (January 2012)



Photograph 7 - (January 2012)



Photograph 8 - (January 2012)



Photograph 10 - (January 2012)


02. Construction Milestones

Construction Milestone

Detail

Target Date

 

 

 

 

On Site Start-up

 

Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works

 

 

May 2009

 

Mock Up Facility

 

 

Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms

 

 

January 2009

 

Topping Out

 

 

Building reach roof top level.  Superstructure complete.

 

 

Quarter 3 2010

 

Weather Tight

 

 

Building sealed from the elements; Windows, doors & roof.

 

 

Quarter 1 2011

 

Internal Finishes

 

 

Viewing a section of the completed internal works.

 

Quarter 1 2011

 

External Finishes

 

 

Landscaping, lighting, signage, way finding.

 

Quarter 1 2012

 

Practical Completion

 

 

Construction Phase Complete, ready for Trust Commissioning.

 

Quarter 2 2012

 

Opening

 

 

New Hospital opens its doors to patients.

 

Quarter 3 2012

 

Official Opening

 

 

Official Opening Ceremony

 

Autumn 2012


03. Subcontractor Appointment

The project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program). A very compliant and qualified local construction industry is prequalifying for involvement in the project.

 

04. Two Month Look Ahead (01 Feb – 31 March 2012)

 
·         All internal fit out and finishes completed
·         All mechanical and electrical services substantially complete.
·         Validation and snagging of internal works substantially complete.
·         Landscaping and external works completed.