Construction Progresss Update - April 2011

New Acute Hospital

For The South West 

ENNISKILLEN

Progress Update



For Works up to 31st March 2011




1. Overview / Current Status


Photograph 1



Photograph 2

 
Photograph 3


Photograph 4


Photograph 5


Photograph 6


Photograph 7


Photograph 8

2. Construction Milestones

Construction Milestone

Detail

Target Date

 

 

 

 

On Site Start-up

 

Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works

 

 

May 2009

 

Mock Up Facility

 

 

Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms

 

 

January 2009

 

Topping Out

 

 

Building reach roof top level.  Superstructure complete.

 

 

Quarter 3 2010

 

Weather Tight

 

 

Building sealed from the elements; Windows, doors & roof.

 

 

Quarter 1 2011

 

Internal Finishes

 

 

Viewing a section of the completed internal works.

 

Quarter 1 2011

 

External Finishes

 

 

Landscaping, lighting, signage, way finding.

 

Quarter 1 2012

 

Practical Completion

 

 

Construction Phase Complete, ready for Trust Commissioning.

 

Quarter 2 2012

 

Opening

 

 

New Hospital opens its doors to patients.

 

Quarter 3 2012

 

Official Opening

 

 

Official Opening Ceremony

 

Autumn 2012

Milestone D

etail Target Date

3. Subcontractor Appointment

 

The project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program). A very compliant and qualified local construction industry is prequalifying for involvement in the project.



4. Two Month Look Ahead (April – May 2011)

·
   
Glazing and curtain walling will be complete.
·       Mains electrical power connected to all buildings.
·       Key Workers envelope will commence.
·       Internal fit out works will be well advanced with the commencement of the installation of final fixtures and fittings.
·       Shaping of the final landscaped areas will commence.