ENNISKILLEN
Progress Update
No 15
For Works up to 31st August 2011
Provided By
Northern Ireland Health Group
1. Overview / Current Status

Photograph 1

Photograph 2

Photograph 3

Photograph 4

Photograph 5

Photograph 6

Photograph 7
2. Construction Milestones
Construction Milestone | Detail | Target Date |
| | |
On Site Start-up | Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works | May 2009 |
Mock Up Facility | Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms | January 2009 |
Topping Out | Building reach roof top level. Superstructure complete. | Quarter 3 2010 |
Weather Tight | Building sealed from the elements; Windows, doors & roof. | Quarter 1 2011 |
Internal Finishes | Viewing a section of the completed internal works. | Quarter 1 2011 |
External Finishes | Landscaping, lighting, signage, way finding. | Quarter 1 2012 |
Practical Completion | Construction Phase Complete, ready for Trust Commissioning. | Quarter 2 2012 |
Opening | New Hospital opens its doors to patients. | Quarter 3 2012 |
Official Opening | Official Opening Ceremony | Autumn 2012 |
3. Subcontractor AppointmentThe project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program). A very compliant and qualified local construction industry is prequalifying for involvemnt in the Project.
4. Two Month Look Ahead (01 October – 30 Nov 2011)
· Significant Completion of internal fit out and finishes· Façade works completion· Landscape seeding and planting commenced· Helipad construction complete· All lifts complete and tested.