Construction Progresss Update - August 2011


New Acute Hospital

For The

South West

 

ENNISKILLEN


Progress Update

No 15

For Works up to 31st August 2011

 

Provided By

Northern Ireland Health Group

1. Overview / Current Status


Photograph 1


Photograph 2


Photograph 3



Photograph 4



Photograph 5



Photograph 6


Photograph 7

2. Construction Milestones

Construction Milestone

Detail

Target Date

 

 

 

On Site Start-up

Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works

May 2009

 Mock Up Facility

 

Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms

January 2009

 Topping Out

 

Building reach roof top level.  Superstructure complete.

Quarter 3 2010

 Weather Tight

 

Building sealed from the elements; Windows, doors & roof.

Quarter 1 2011

 Internal Finishes

 

Viewing a section of the completed internal works.

Quarter 1 2011

 External Finishes

 

Landscaping, lighting, signage, way finding.

Quarter 1 2012

Practical Completion

Construction Phase Complete, ready for Trust Commissioning.

Quarter 2 2012

Opening

 

New Hospital opens its doors to patients.

Quarter 3 2012

 Official Opening

 Official Opening Ceremony

 Autumn 2012


3. Subcontractor Appointment

The project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program).  A very compliant and qualified local construction industry is prequalifying for involvemnt in the Project.


4. Two Month Look Ahead (01 October – 30 Nov 2011)

 

·         Significant Completion of internal fit out and finishes

·         Façade works completion

·         Landscape seeding and planting commenced

·         Helipad construction complete

·         All lifts complete and tested.



 