New Acute Hospital For The South West
ENNISKILLEN

Progress Update
No 16 For Works up to 31st October 2011 Provided By Northern Ireland Health Group 1. Overview / Current Status
 Photograph 1 (October 2011)
 Photograph 2 (October 2011)
 Photograph 3 (October 2011)
 Photograph 4 (October 2011)
 Photograph 5 (October 2011)
 Photograph 6 (October 2011)
 Photograph 7 (October 2011)
2. Construction Milestones
Construction Milestone | Detail | Target Date | | | |
On Site Start-up | Site Setup; Management & Workers Amenities, Established Site Access Protocols, Piling & Ground Works | May 2009 | Mock Up Facility | Viewing of Prototypes of key areas of the new facilities including the single room and en-suite bathrooms | January 2009 | Topping Out | Building reach roof top level. Superstructure complete. | Quarter 3 2010 | Weather Tight | Building sealed from the elements; Windows, doors & roof. | Quarter 1 2011 | Internal Finishes | Viewing a section of the completed internal works. | Quarter 1 2011 | External Finishes | Landscaping, lighting, signage, way finding. | Quarter 1 2012 | Practical Completion | Construction Phase Complete, ready for Trust Commissioning. | Quarter 2 2012 | Opening | New Hospital opens its doors to patients. | Quarter 3 2012 | Official Opening | Official Opening Ceremony | Autumn 2012 |
3. Subcontractor Appointment
The project continues to participate in and gain benefit from the supply chain model set up by SERP (Social Economic Regeneration Program). A very compliant and qualified local construction industry is prequalifying for involvement in the project.
4. Two Month Look Ahead (01 Dec – 31 Jan 2012)
· All construction significantly complete. · Lights on to all buildings. · Heat on to all buildings. · Validation of completed areas well advanced. · Specialist areas of operating theatres, sterile suites etc. well progressed. · Commissioning of Mechanical / Electrical services well progressed. · Biomass boilers operable and producing steam. |